Texaco Oil Refinery, Anacortes, Washington
details...
The Client needed to replace a C.O. boiler which was in an area
with limited access. The standard approach was a six-week process
which included tearing the boiler down in pieces, replacing the
tubes and then rebuilding the boiler. Instead, in conjunction with
the contractor, Sicklesteel devised a plan to fabricate a new 179
ton boiler off-site, roll it to a DEMAG TC3200 (625 ton) crane,
pick the old boiler out at a 110’ radius, set it off to one side
and then swing the crane around and set the new boiler in. This
plan reduced the change out of the boiler down to under 10 days,
saving the client considerable oil to oil time.
Asarco,
Helena, Montana & El Paso, Texas
details...
The Client had a limited access area with minimal clearance to
lift heat exchangers during a plant turnaround. Sicklesteel proposed
utilization of a DEMAG TC1200 (308 ton) to lift exchangers, weighing
over 100,000lbs, at a 79’ radius.
ARCO
Oil Refinery, Ferndale, Washington
details...
The Client improved an existing unit necessitating the erection
of 2 vessels with a 6-month delay between lifts. For the first
lift, Sicklesteel proposed utilizing a DEMAG TC2000 with 157’ of
main boom to lift the 286,000lb vessel out to a 45’ radius. For
the second lift, Sicklesteel proposed utilizing a LTL-350 (transilift)
with 220’ of main boom as the erection crane for the 424,000lb
vessel as well as two (2) AC615’s to serve as tandem tail cranes
to assist with rotating the vessel in the air from the horizontal
to vertical position. Sicklesteel saved the client $300,000 of
crane costs and completed the project 5 days ahead of schedule.
Georgia
Pacific Corporation, Bellingham, Washington
details...
The Client needed to lift 79 ton Yankee Drier off of barge and
install it on the 2nd floor through an opening in the side of the
building. Sicklesteel proposed utilizing a DEMAG TC1200 (308 ton)
which would lift the drier to the opening and also designed a mid-air
transfer of the load from the DEMAG TC1200 to an overhead crane
stationed within the building.
ARCO
Oil Refinery, Ferndale, Washington
details...
The Client needed to replace a convection box at the top of a
vessel during the middle of a turnaround. Sicklesteel proposed
utilizing a MANITIWOC 4100 Ringer positioned within the unit so
as not to block a main roadway of the plant. Sicklesteel also assisted
in the design of spreader bars in order to accommodate the limited
lifting clearances. Project was finished ahead of schedule and
under budget.
Boise
Cascade, St. Helens, Oregon
details...
The plant needed to replace air heater in a recovery boiler but
did not have adequate room to position a large crane for the required
lifts. Sicklesteel utilized the AutoCAD system to select a large
crane which would meet the clearance restrictions as well as perform
the work economically. The project was completed ahead of schedule
and under budget.
Potlatch
Paper Mill, Lewiston, Idaho
details...
The Client needed to lift piping within plant. Lift required reaching
60’ in from an obstruction 140’
in the air. Sicklesteel proposed utilizing a KRUPP 140GMT-AT with
146’ of main boom and 80’ of luffing jib. Project was completed
ahead of schedule and within budget constraints.
Chevron
Oil Refinery, Richmond, California
details...
The Client needed to lift a vessel and complete the entire mobilization,
lift and demobilization as quickly as possible. The only solution
the client believed to be available was the installation of guy-derricks
to make the lift. Sicklesteel utilized its AutoCAD system to provide
an alternate proposal of positioning a DEMAG TC1200 (308 ton) in
an area that contained clearances of less than 1’. Mobilization,
lifting the vessel and demobilization were completed in less than
20 hours and well below budget.
Dow
Chemical, Plaquemine, Louisiana
details...
The Client’s project involved placing numerous pre-manufactured
modular sections to expand facility as well as many vessels with
weights up to 200 tons. Sicklesteel proposed utilizing a DEMAG
TC3200 (625 ton) with full superlift in order to accomplish the
lifts. A key to the projects success was Sicklesteel’s design of
a track assembly to transport the superlift counterweight on a
self-contained framework and independent of the crane. This allowed
the counterweight to be moved into position after the crane was
set-up thereby maximizing the on-hook utilization of the DEMAG
TC3200. The project was completed ahead of schedule and substantially
under budget constraints.
Ketchikan
Pulp Mill, Ketchikan, Alaska
details...
The Client needed to erect a pressure vessel in a restrictive
area. Sicklesteel proposed utilizing a smaller crane in an alleyway
instead of a ringer sitting on the outside of the unit. Sicklesteel
utilized CAD to demonstrate the lift and portray the critical clearances.
Sicklesteel performed the lift with a KRUPP 140GMT-AT (165 ton)
saving the client considerable time and nearly $100,000 in crane
costs.
James
River Pulp Mill, Camas, Washington
details...
Sicklesteel Cranes Utilized CAD to design assembly of a DEMAG
TC1200 (308 ton) configured with 177’
main and 118’ of jib. Site required boom to be erected between
railroad tunnel and pipe rack (120’ apart). Sicklesteel Cranes
initially positioned crane in railroad tunnel and utilized 3 other
cranes for assembling boom in the air. Site required passage of
rail cars through tunnel in 12 hour increments and also had uneven
ground coming off of railroad grade. Sicklesteel completed the
project ahead of schedule and under budget.